Photo report from the construction site of the SYMBOL residential complex for December 2023 from the Credo company:
Completed the brickwork of the outer walls on the 10th floor
We are completing the brickwork of inter-apartment and interior walls
We have completed the masonry of technical rooms, storerooms and an electrical switchboard in the underground parking lot
We have completed the installation of window structures on the 2-7th floors and continue on the 8-10th
We have started work on the roofing